Brotman Hall (BH) Suite 377 Renovation
This project consisted of renovating suite377 for Student Affairs. The renovation included 6 new offices, an open office area for 4 cubical stations, 3 hoteling stations, reception, conference room, copy/scan room and kitchenette. The mechanical system was reconfigured for the new layout and plumbing services was added to the kitchenette. New LED lighting throughout the space along with updated finishes to compliment the departments branding/identity.
- Total Project Cost: $1,054,634.00
- Construction Start Date: October 2022
- Construction Completion Date: February 2023
- Project Delivery Method: CM at Risk
- Architect: Moreto, Mathison and Associates
- Construction Manager: CSULB Facilities Project Services
- University Design and Construction Team:
- Marc Joves, Project Manager
- Jon Root, Construction Manager
- Tammy Hinds, Inspector of Record