HR&L Parkside Fire Alarm
This project provides a new Notifier fire alarm system to all Parkside buildings. The system will update all fire alarm devices to meet hte current standards and code compliance. Along with the fire alarm, upgrade, there will be an update on the communication infrastructure network to fiber cable.
- Total Project Cost: $4,827,141
- Construction Start Date: May 2024
- Construction Completion Date: August 2024
- Project Delivery Method: Construction Manager at Risk (CM@R)
- Architect: MMA/P2S
- Construction Manager at Risk: 2H Construction
- University Design and Construction Team:
- Marc Joves, Project Manager
- 2H Construction, Construction Manager
- Ed Puga, Inspector of Record