CPAC HVAC MERV Upgrade

The project will include replacing twenty existing (20) rooftop packaged HVAC units with "like for like" HVAC units with Minimum Efficiency Reporting Value (MERV) filter rating capabilities. HVAC nits with MERV 13 filters, when installed as part of this project, will remove the particles that contain aerosol viruses from being spread through central HVAC system, and facilitate minimizing the potential spread of the pandemic causing virus transmission within building facilities. 

  • Total Project Cost: $1,344,056
  • Construction State Date: May 31, 2023
  • Construction Completion Date: March 1, 2024
  • Project Delivery Method: Construction Manager at Risk (CM@R)
  • Architect: Goss Engineering
  • Construction Manager at Risk: Brascia Builders Inc.
  • University Design and Construction Team: 
    • Marc Joves, Project Manager 
    • Satish Sadhu, Construction Engineer
    • Dana Morley, Project Engineer 
    • Thomas Sanchez, Inspector of Record