Brotman Hall Suite 123 Enrollment Services Phase 3

Suite 123 will undergo a complete renovation.  The area will still be used for office space, but it will be gutted in order to accommodate a new space efficient layout that consists of some private offices, many open work stations, two huddle areas, two conference rooms, and a  break room. The lighting fixtures and mechanical ductwork will be replaced to accommodate the new layout of the space, and there will be all new interior finishes, including office furniture.

  • Total Project Cost:  $5,179,880 
  • Construction Start Date:  October 1, 2019
  • Construction Completion Date: April 30, 2020
  • Project Delivery Method:  Construction Manager at Risk (CMAR)
  • Architect: Cuningham Group
  • Construction Manager at Risk:  Swinerton Builders
  • University Design and Construction Team:
    • Stephanie Gutierrez, Project Manager
    • Marie-Jeanne Ayoub, Construction Manager
    • Dana Morley, Project Engineer
    • Tammy Hinds, Inspector of Record